Last Two Weeks:

  • Montgomery completed the water main work this week.
  • Montgomery and the Township Water Department pressure tested and disinfected the new water main.
  • Montgomery worked on restoration work along Pine Island Drive and Pine Island Court.
  • Driveway paving and road shoulder repairs are scheduled for TOMORROW, JUNE 24.

 

Next Week:

  • Montgomery will install the remaining water service stubs on Pine Island Drive and Pine Island Court.
  • Montgomery will begin road work along Pine Island Drive. The existing asphalt surface will be crushed and left in place. Montgomery will regrade the aggregate and all of Pine Island Court will receive new asphalt.

 

Please contact any project representative if you have questions or concerns.