Last Two Weeks:

  • Schippers completed water main installation on Herrington Avenue and 10 Mile Road.
  • Schippers tested the first section of water main on Herrington Avenue
  • Schippers began to fill the new water main along 10 Mile Road in preparation for testing next week.
  • Schippers began water service installation along Herrington Avenue today.

 

Next Week:

  • Schippers will continue water service installation along Herrington Avenue.
  • Schippers will pressure test and disinfect the new water main along 10 Mile Road.