Last Two Weeks:
- Integrity Tree began tree removal activities.
- Montgomery Excavating installed 8-inch water main along Offroad Drive.
- Montgomery Excavating began installing 12-inch water main along Jewell Avenue, starting at 10 Mile Road and working north.
- Montgomery Excavating should complete 8-inch water main installation along Green Timbers Drive today.
- Jewell Avenue was closed to thru traffic.
Next Week:
- Montgomery Excavating will continue installing 12-inch water main along Jewell Avenue.
- Jewell Avenue will be closed to thru traffic.