Current Status/Progress Report

To date, 93% of houses in the project area have a General Contractor lined up to install the private portion of their water service. Only 15 houses remain to be connected to the municipal water system, 75% of the project area is already connected. If you have not contacted a prequalified General Contractor to install your water service, you must do so as soon as possible. All water services are ready for connection. If you have any questions about the process, please reach out to Jeremy Kamp, contact information is to the left.