Today, June 26, the base course of asphalt pavement will be placed on Chandler Drive. This will leave the new pavement about 1.5 inches lower than the existing pavement. The top course of asphalt will be placed later.

Dykema has experienced some delays with the water main testing process for the water main along Herrington at Chandler Drive. This has required extra flushing of the main and has delayed the installation of water service stubs along Herrington. The testing and water sampling will continue through this coming weekend.

Water service quotation forms have been received for about 85% of the houses along Chandler and Herrington. If residents have not yet talked to a contractor about installing the private water service, they should do so ASAP in order to meet the 60-day connection requirement.

 

What to Expect Next Week (June 29 – July 3)

 

Projected Timeline