Progress Report: Montgomery Excavating has placed new aggregate base material over a prepared sub base on Venna Place and Vida Circle. Concrete crews have completed most curb and gutter placement on Venna Place and Vida Circle, and some concrete approaches. Final water main connections were made, completing underground pipe installation on the project.

Upcoming Work: Concrete work on Venna Place and Vida Circle will be completed and Montgomery Excavating will continue the restoration process by preparing the roads for asphalt paving and by spreading topsoil for turf restoration.

Extra Notes: Access to driveways on Venna Place and Vida Circle will be limited for a duration of time to accommodate concrete curb and driveway approach construction including time to allow the concrete to cure. Montogomery Excavating will notify residents affected by this disturbance a prior to concrete construction.