Work completed/in progress from this past week:
- 152nd Avenue intersection paved and opened to traffic.
- Leak detection in 36″ transmission main between 160th through 152nd
- Drilling contractor continues to remove material for pipe installation beneath Pine Creek.
- 36″ transmission main construction east of 144th progressed to approximately 500′ E of the eastern Winter Oaks drive.
- Water service and sanitary lateral verification and replacement.
- Started fine grading aggregate base between 160th and 152nd.
- Precision Trenching began work to relocate and underground HBPW electric service between Aniline and Division.
- Milled north side of Lakewood between 152nd and 144th.
Anticipated activities for next week include:
- Close 160th Ave intersection and start work on tie-in to 30″ interconnect.
- ID leak between 160th and 152nd and repair as necessary.
- Pressure test and disinfect transmission main between 160th and 152nd
- HDD crew continue 54” ream pass and pull back 42″ pipe.
- Water service and sanitary lateral verification and replacement.
- Dewatering setups as necessary.
- Continue transmission main installation east of 144th