Update – Week of June 6, 2022:

Construction will begin at the intersection of Elizabeth and Alice with the replacement of some sanitary sewer main. This will likely take the remainder of the week. This involves about 100-feet of sanitary sewer pipe installation on the south side of Alice, going west from Elizabeth. Traffic should not be impacted. Workers will then move over to Lakeview Street near Misco and begin pavement removal for the following week of work.

 

Work Expected – Week of June 13, 2022:

Pavement removal on Lakeview Street from Misco Drive north and sanitary sewer main replacement will begin at Misco and crews will work their way north. Sewer work will likely take all week to get to Lewis. Access to driveways will be maintained, but likely from one direction only.