This Week:

  • Brenner Excavating connected their new water main to the water main installed by Montgomery Excavating at the intersection of Pine Island Drive and 10 Mile Road.
  • Brenner Excavating and the Plainfield Water Department filled the 16-inch water main and completed pressure testing and disinfection testing between Pine Island Drive and the Freska Lake Drain.
  • Brenner Excavating continued road work and storm sewer work.

 

Next Week:

Brenner Excavating will not be on site next Monday due to the holiday.

Remaining water main work is as follows:

  • Brenner Excavating will continue water service stub installation between Pine Island Drive and the Freska Lake Drain.
  • The last of the 16-inch water main will be installed across the Freska Lake Drain.

 

Please contact any project representative if you have questions or concerns.