This Week:
- B&L Excavation completed the water main installation on Squirewood Court.
- B&L Excavation and the Plainfield Water Department filled the new water main and completed pressure testing and disinfection testing this week.
- B&L Excavation worked on cleaning up the site in preparation for the long holiday weekend.
Next Week:
- B&L will not be on site next Monday due to the holiday.
- Pending passing test results on Saturday (tomorrow), B&L will begin installing water service stubs on Wednesday. This work should last through the end of next week.
- B&L will also begin prepping for concrete work which is tentatively scheduled for the week after next week.
Please contact any project representative if you have questions or concerns.