Progress Report:

  • Maple St. Storm Sewer: Storm sewer installation on Maple Street between Monroe and Fremont Street was completed Tuesday of this week.
  • Fremont St. Storm Sewer: Storm Sewer Installation on Fremont Street has begun and is anticipated to be complete by the end of the week.
  • Lincoln St. Water Main: Water service installation along N. Lincoln Street between Courtland and Bridge Streets has begun and will be complete by the end of the week.
  • Lincoln St. Sanitary Sewer: Sanitary sewer installation on Lincoln Street between Courtland and Maple Streets was completed this week. Lateral installation along Lincoln Street will begin by the end of this week and will continue next week.

 

Up Next:

  • Maple Street: Storm sewer lateral installation on Maple and Fremont Street will begin next week.
  • Lincoln Street: Sanitary sewer lateral installation along Lincoln has begun this week and will continue into next week.