Progress Report

This week:

  • Schippers finished installing new water services on Bonanza Drive and Bonneville Drive.
  • Schippers began water main construction in Rockvalley Drive.
 

Next week:

  • Base course paving in Rockhill Drive is rescheduled for middle of next week.
  • Water main construction in Rockvalley Drive and easement between Rockvalley Drive and Bonneville Drive will be completed.
  • Schippers will continue to reconstruct the road on Bonneville Drive and Bonanza Drive.
  • Schippers subcontractor, Lee’s Trenching, will install water services across Plainfield Avenue between 5 Mile Road and Omega Drive.
 

Please contact a project representative if you have questions or concerns.

 

What to Expect

June

  • Water main and water service construction on Rockvalley Drive.
 

Late June & July

  • Water main construction on Bonneville Drive, north of Brisam, and court streets.
 

August

  • Water service construction on Bonneville Drive, north of Brisam, and court streets.
 

Long Term

  • Schippers’ overall project schedule anticipates the total project, including road paving and lawn restoration, being complete in late summer. Schippers is currently on track to meet this schedule.

 

Important Information

There will be times that the area in front of your homes is torn up and you will have limited access to your home. Please let us know if you have any special access needs and we will do our best to make arrangements with you.

The contractor has set up a bank of temporary mailboxes on Brisam Street, west of Bonneville Drive. If you are within the construction area, your mail service has been temporarily relocated to here. The contractor is also coordinating with the trash haulers in the area to ensure that the trash is picked up during construction. Please bring your cans to the end of your driveway as you typically would, and the contractor will move them as necessary for pickup and return them at the end of the day.

 

Project Timeline

  • June
    • Water main and water service construction in Rockvalley Dr.
    • Water service construction along Plainfield Ave.
    • Road reconstruction in Rockhill Dr, Bonneville Dr, and Bonanza Dr.
  • End of June – end of September
    • Water main and water service construction on Bonneville Dr. and court streets north of Brisam St.