This week:

  • Dykema completed water service stub installation on Stoneridge Drive except for one service which requires different equipment due to the length of the service stub. This work is scheduled for next Wednesday.
  • Dykema started water service stub installation in the 43 North neighborhood.
  • Dykema started road reconstruction in Wolven Avenue.
 

Next week:

  • Dykema will finish water service stub installation in the 43 North Neighborhood.
  • Dykema will start water service stub installation on 11 Mile Road.
  • Dykema will start water main construction on Elstner Avenue.
  • Dykema will continue to reconstruct Wolven Avenue and complete restoration.
 

Please contact a project representative if you have questions or concerns.

 

What to Expect

June
  • Water service installation in the 43 North neighborhood and along 11 Mile Road.
  • Water main construction along Elstner Avenue.
  • Road reconstruction along Wolven Avenue.
  • Installation of water services on private property. This work will be coordinated between each individual property owner and the contractor you select to install your water service.
 
Long-Term
  • Dykema’s overall project schedule anticipates the total project, including road paving and lawn restoration, being complete in late August 2021. Dykema is currently ahead of this schedule and on track to complete the project in August.

 

Important Information

There will be times that the area in front of your homes is torn up and you will have limited access to your home. Please let us know if you have any special access needs and we will do our best to make arrangements with you.

The contractor will be contacting you to make arrangements for mail delivery and garbage collection. Please let us know if you have any problems with this.

 

Anticipated Project Timeline

JuneWolven Avenue and Bent Tree Ridge road reconstruction
JuneStoneridge Drive water service installation and restoration
June – July43 North water service installation and restoration
June – July11 Mile Road water service installation and restoration
June – AugustElstner Avenue water main, water service installation, and restoration