Well the “road” (pun intended) was long and grueling at times, however, we are in the very final push completing this project! With a beautiful new asphalt surface installed, pavement markings complete, North Shore Drive is looking great! There are a few details left to accomplish by the contractor which will be completed next week.
Project Schedule
- Week of June 1 – 5
- Milbocker had subcontractors lay down the pavement markings, start installing the traffic control signage, and they continued the final restoration efforts.
- Week of June 8 – 12
- Milbocker will be out finishing up some restoration of yards, driveways, retaining walls and irrigation, as well as hydro-seeding areas calling for grass to be replanted. Milbocker’s subcontractor will also be out finishing up the traffic control signage.