The Red Arrow Highway closure immediately north of Berrien Street has been pushed back one more week and will now occur June 16 through June 18. Access to local businesses will be maintained via Lakeshore Drive.

Kalin continues to work late nights and Saturdays to get the Union Pier intersection work done as quickly as possible. Schedule delays are the result of challenging underground construction conditions. We appreciate everyone’s continued patience and understanding to-date.

 

Work completed this past week:

  • 24-inch sanitary sewer installation in Townline Avenue continues.
  • Two sanitary manhole structures were set.
 
 

What to expect next week (June 8 – 13):

  • Complete sanitary sewer installation in Union Pier intersection.
  • Transfer flow to new meter piping.