Current Road Closures

  • Fifth Street from Merrill Avenue to Mason Avenue
  • Fourth Street from Merrill Avenue to Mason Avenue
 

Work Completed This Week

  • Jackson-Merkey removed the asphalt and various concrete removals on Fifth Street from the alley to Merrill Avenue.
  • Jackson-Merkey removed the asphalt on Fourth Street at the alley.
  • Jackson-Merkey began installation of the sanitary sewer on Fifth Street at Merrill Avenue.
 

Anticipated Work Next Week

  • Jackson Merkey plans to continue the sanitary sewer on Fifth Street and continue into the alley between Merrill Ave. and Mason Ave.