Work Completed This Past Week
- Contractor began installing water services to vacant lots between the water main and the sidewalk.
- Contractor installed water main pipe in Hume between Baker and Leahy Streets.
- Water main pipe in Leahy Street was cleaned and flushed and tested for connection to the City System.
Work Anticipated Week of June 5, 2023
- New water main will be tied in at the mid-block between Hume and Hovey to Barney.
- Finish the water main in Hume between Baker and Leahy.
- Clean, flush and test the new water main in Hume.
- Replace water services on Leahy between Sherman and just north of Hovey.
Work Anticipated Week of June 12, 2023
- Connect new water main in Hume to the new water main in Leahy.
- Begin preparing to tie-in the new water mains to all the points to the existing system at Barney, Baker and Hume – This may involve water interruptions. Customers will be notified ahead of time.
- Water services will continue to be replaced.