Work Completed This Week

West Michigan Dirtworks completed pressure testing of the final section of force main. Following completion of the pressure test the Spring Lake Pump Station was bypassed and the final connections were made to the pump station. The new Grand River crossing pipe is operational and in use!
West Michigan Dirtworks began reconstruction of Exchange Street, approximately 50% of the new aggregate base has been installed. The remainder of the roadway was removed as well.
Anticipated Work Next Week

West Michigan Dirtworks crews will continue reconstruction of Exchange Street and Division Street. Work may begin on restoration of locations in Grand Haven by weeks end.
Comments

West Michigan Dirtworks replacement of the water main on Cutler Street has been added to the project. This work will likely delay completion of Cutler Street until after the June 28 project completion date. All other portions of the project will be completed by the original Contract times.