Search
Close this search box.

Progress Report: Progress continued on Storm Sewer and Sanitary Lateral connections on River Street between Randall Avenue and Court Street.

Upcoming Work: K&R will continue storm sewer construction and sanitary connections on River Street. Progress will continue to the south. Crews will begin preparing the construction site for road restoration after all pipe installation is completed. Road Grading will occur on River Street south of O’Malley Drive starting early next week.