Lots of progress this week! Tinkham is starting to look like a road again with paving and more concrete being completed.
Work Completed This Week
- The first course of asphalt was laid from Lakeshore to Gaylord Street.
- Aggregate was placed from St. Paul to Williams.
- Concrete curb and gutter was completed from Gaylord to Williams. All curb on the project is now complete.
- Manhole covers were raised west of Gaylord.
Anticipated Work Next Week
- Install all remaining concrete sidewalk and drive approaches.
- Complete aggregate grading in preparation for paving east of Gaylord.
- Possibly by end of the week, the first course of asphalt will be placed east of Gaylord; however, this is more likely to happen the week of the 17th.