- Prein&Newhof had a survey crew on site to stake the water main on Squirewood Drive.
- B&L Excavation began moving equipment on site and will begin water main construction at Squirewood Drive.
- Miss Dig contractors were on site marking the location of existing utilities on Squirewood Drive and Squirewood Court in preparation for water main construction next week. It is critical that residents do not remove any flags or stakes that were recently installed as this will only slow the construction process down.
Next Week:
- B&L anticipates they will start water main construction on Squirewood Drive middle of next week.
Please contact any project representative if you have questions or concerns.