This Week:
- Montgomery completed tree clearing between Pine Island Drive and Pine Island Court.
- Montgomery completed grading in the area the trees were cleared in preparation for water main construction.
- Montgomery installed a steel casing via bore & jack construction under Pine Island Drive. This steel casing will carry the 16-inch water main in it without having to dig up the road.
Next Week:
- Montgomery will begin water main construction from Pine Island Drive up the hill to Pine Island Court.
- Montgomery will remove previously installed 16-inch water main along Pine Island Drive which will no longer be needed after the re-route is complete.
- Montgomery will begin to remove the 8-inch water main that was previously installed along Pine Island Court and replace it with 16-inch water main.
- Depending on progress, Montgomery may begin the second bore & jack under Pine Island Drive at the north end of Pine Island Court.
Please contact any project representative if you have questions or concerns.