Work continues in anticipation of the June 28th dedication. 

  • The first soccer field that was seeded has been mowed while the baseball and softball field and grass areas around these fields continues to grow in.
  • All concrete work on site is completed.
  • Pickleball court surfacing is scheduled for the week of June 21st along with surface course of asphalt.
  • Restroom fixtures are being set. 
  • Final seeding of the last of the soccer fields and other common areas continues. 
  • The JoJo Jogging trail is complete. 
  • Site amenities are being assembled with benches, picnic tables and bleachers appearing throughout the site.