Progress Report:  K&R has started staging equipment on the project site, and construction signage has been installed. MISS DIG has located underground utilities on the project limits with multi colored paint and flags.

Upcoming Work:  Construction activity on River Street will begin on March 18, 2024. The Contractor will start road removals and tree removals on Monday, March 18, and will continue with locating existing utilities with a vac truck. Access will be maintained throughout the project site with gravel materials. Please use caution when driving or walking around construction equipment.