Construction of Holland BPW Improvements is starting!

Starting next week, Lakewood Boulevard will be closed to thru traffic between 160th and 152nd and between 152nd and 144th for the next several months. Traffic between 160th and 152nd will be detoured to James Street. Traffic between 152nd and 144th will be detoured to Ottawa Beach Road. 160th, 152nd, and 144th Avenue intersections will remain open for the time being.

Please be safe and use caution when driving through construction zones.

Work anticipated for next week includes the following:

  • Lakewood closure between 160th and 152nd. Traffic detoured to James Street.
  • Lakewood closure between 152nd and 144th. Traffic detoured to Ottawa Beach.
  • Coordination with residents between 160th and 152nd to relocate mailboxes and facilitate garbage pick-up.
  • Grading on either side of Pine Creek for trenchless pipe installation beneath creek.
  • Remove the north lane and some segments of the south lane of Lakewood between 160th and 152nd.
  • Prepare for and possibly start 36″ water main installation.