Work on Mill Pond Trail is in full swing! Water main installation is progressing from Silver Creek to the east along Mill Pond Trail and will continue for the foreseeable future.
Work Completed this week
- Tree removal was completed.
- Approximately 800 ft of water main was installed on Mill Pond Trail progressing east from Silver Creek Road.
Anticipated Work for the Coming Week
- Water main installation along Mill Pond Trail will continue.
- Water service installation will begin along Silver Creek, this work will be scheduled with each property owner.
Please be aware of the construction work, do not assume that equipment operators can see you. Do not approach heavy equipment.