Progress Report:

  • Tree clearing was completed along Northland Drive and Kuttshill Drive this week.
  • Dykema Excavators completed water main construction along the south side of Northland Drive.
  • Due to the snowfall today (Friday), no water main work will take place on site to allow plow trucks to clear the roads.
  • Underground utilities were located on the north side of Northland Drive in preparation for water main construction next week.

 

Upcoming Work:

  • Dykema will move their equipment to Northland Drive (north of M-44) and begin water main construction heading north along Northland Drive.
  • Marksmen Contracting, Dykema’s bore & jack subcontractor, will be mobilizing to the site middle of next week and begin setting up their boring pits.
  • Depending on how the bore & jack pit set up goes, Marksman may begin pushing the 30″ steel casing under M-44 by the end of next week.