This was another good week for pipe installation even with the snow squall at the end! Water main mainline installation is nearing completion on Center Street and work on West Street is around the corner.
Work Completed This Week
- Water main is currently installed from Apple Avenue to south of Vine. Most of the installation is anticipated to be complete next week.
- Water main from Apple to McLaughlin has been fully tested and disinfected, connection to the system is anticipated in the next week.
- Water main from McLaughlin to Vine is installed and undergoing final testing.
- Water main is continuing to be installed south of Vine.
Anticipated Work
- Contractor will continue working south installing water main south of Vine.
- Connection of the first section of pipe to the water system is tentatively scheduled for March 28.
- Final testing and disinfecting of the pipe south of McLaughlin will be ongoing.