Work Completed This Week

  • Lift station valve chamber and bypass connection is complete.
  • The forcemain extension between Southern Avenue and Grand Avenue is drilled with forcemain in place.
  • The 10-inch forcemain tie-in to the valve chamber has been made.
  • Surface removal of Crowley Street was performed Tuesday, while drive approaches and curb removal has begun.

 

Anticipated Work Next Week

  • The forcemain discharge manhole will be installed in a new location north of Grand Avenue.
  • Forcemain installation will begin on Crowley Street by open cutting.
  • Work at the Young Avenue lift station will continue, including electrical panel installation.