Work Completed this week
- Approximately 1,600 ft of water main was installed on Mill Pond Trail progressing east from Silver Creek Road. The crews are approaching the halfway point to the end of the line.
- Water service installation has begun on Silver Creek Road with 4 houses being officially connected to the new water main.
Anticipated Work for the Coming Week
- Water main installation along Mill Pond Trail will continue.
- Testing of portions of the new water main on Mill Pond Trail may begin in the next week.
- Water service installation will continue along Silver Creek, this work will be scheduled with each property owner.
Please be aware of the construction work, do not assume that equipment operators can see you. Do not approach heavy equipment.