This Week:

  • Montgomery completed water main installation on Northgate (south of Eldon).
  • Montgomery worked with the Plainfield Water Department to disinfect the new water mains on the south half of Daylor and Northgate (north of Eldon)

Next Week:

  • Montgomery will work with the Plainfield Water Department to pressure test and disinfect the new water main on Northgate (south of Eldon).
  • Montgomery will begin installing water services on Daylor and then move to Northgate (north of Eldon).
  • Double KK Underground will be on site Monday or Tuesday to directionally-drill new water services under the road for Montgomery.