This Week:
- Montgomery completed water main installation on Northgate (south of Eldon).
- Montgomery worked with the Plainfield Water Department to disinfect the new water mains on the south half of Daylor and Northgate (north of Eldon)
Next Week:
- Montgomery will work with the Plainfield Water Department to pressure test and disinfect the new water main on Northgate (south of Eldon).
- Montgomery will begin installing water services on Daylor and then move to Northgate (north of Eldon).
- Double KK Underground will be on site Monday or Tuesday to directionally-drill new water services under the road for Montgomery.