Underground pipe installation is in full swing with significant progress being made in the Edgewater and Wilcox intersection.

Work Completed This Week

  • Installed sanitary sewer, water main and portions of storm sewer in the Edgewater and Wilcox intersectoin. This has been a slow process due to the amount of utilities in the ground and maintaining access for residents on Edgewater.
  • Completed the bore and jack installation in the alley between Walnut and Cherry. Work on connecting the services is ongoing.

Anticipated Work

  • Sanitary sewer and water main installation on Edgewater.
  • Continued work in the alley for final connection of services.