This Week:
- CL Trucking completed water main construction on Winding Ridge Trail on Wednesday.
- CL Trucking began water main construction on Garden Gate Drive on Thursday.
Next Week:
- Water main construction will be completed on Garden Gate Drive and Court.
- Water main construction will begin on Oakwoods Trail.