This Week:
- Tree clearing began along Pine Island Drive and Pine Island Court.
- Montgomery mobilized equipment to the site and began preparatory construction activities.
Next Week:
- Montgomery will begin water main construction at House Street and work north to Pine Island Court.
- Pine Island Drive is under a traffic shift between 10 Mile Road and 9 Mile Road for water main construction along Pine Island Drive.
- 10 Mile Road will close Monday, April 3, between Pine Island Drive and Algoma Avenue. Posted detour route is Pine Island Drive to Post Drive to US-131.
Please contact any project representative below if you have questions or concerns.