Work Completed this past week (March 3-7)
- Meeting at City Hall Monday night
- Dial-a-Ride (Niles) notified of construction location and exchanged contact info.
- Red Bud closed between 4th and Front St. 3rd Street/Red Bud intersection still drivable and traffic can exit Red Bud to the North.
- Pulverizing delayed 2 days due to rain but began grinding 3rd Street Thursday (3/6)
- Concrete footings/walls poured for new Flume at WWTP.
- Contractor started removing sidewalk along Red Bud for water main install.
- Curb box installed at Flume for water service to spray out bin, water turned back on to Headworks Bld at WWTP.
- Chop onsite to grind stumps on Dewey and at WWTP.
- Construction Photos can be viewed here.
Work planned for this week (March 10-14)
- Water Main pipe delivery scheduled for Monday (3/10).
- Milling of Red Bud between Front Street and 4th Street scheduled for Monday (3/10). 3rd Street intersection will remain open.
- Road Closure on 3rd Street, East of Fitness Center driveway, scheduled for March 10th. Access to Fitness Center will be possible from the West (Red Bud).
- Monday (3/10), Water Treatment unit to be delivered to 3rd Start up of system scheduled for Tuesday.
- Monday (3/10), Begin water main install on Red Bud starting at 3rd Street and heading South (Red Bud/3rd Street intersection will remain open)
- Monday (3/10), water main install begins on Dewey for horizontal directional drill under the creek
- Tuesday (3/11), Install H-Piles for aerial crossing
- Tuesday (3/11) review utility conflicts with AEP power poles in the field.
- Wednesday (3/12), begin high pH excavation area on 3rd Street just East of Fitness Center driveway (access to Fitness Center from Red Bud/3rd Street). Expect this work to last 1 week.