Progress Report:

On February 12, 2024, the Plainfield Charter Township Board of Trustees awarded the transmission main construction contract to Dykema Excavators of Grand Rapids, MI. Dykema Excavators intends to start construction activities on site on Monday, March 18, 2024. The transmission main will be built from the south end at Brewer Avenue and construction will progress north up to Kuttshill Drive. Prior to construction, trees within the public road rights-of-way will be cleared as necessary for water main construction. If you would like to keep the wood generated from the tree clearing along your property, please reach out to one of the project contacts to the left.

In the coming weeks, you will begin to see flags marking existing underground utilities, construction stakes, water main materials, and equipment show up along the project route.

Construction is anticipated to be complete by mid-May.

If you have any questions about construction or the potential impacts it may have on you, please contact Jeremy Kamp at (616) 432-6709.