This Week:

  • Montgomery continued restoration work along the west side of Pine Island Drive by installing driveway culverts, restoring roadside slopes, and placing topsoil and hydroseed.
  • Montgomery began installing water services at the south end of the project.
  • Montgomery found a leak in the water main north of Pine Island Court during pressure testing. The leak was repaired, and a successful pressure test was completed. Montgomery began the disinfection testing process of this section of pipe.

 

Next Week:

  • Montgomery will continue to install water services at the south end of Pine Island Drive pending passing disinfection test results.

 

Please contact any project representative if you have questions or concerns.