Work to Date

  • Watermain has been placed along Burger between Goodwood and Tuscany.
    • The main has passed all testing and has been tied into the existing system.
    • Crews have continued stubbing water services out to the right of way line.
  • Watermain has been placed along Tripoli between Burger and Tuscany and on Tripoli Court.
    • The main has passed all testing and has been tied into the existing system.
    • Crews have begun stubbing water services out to the right of way line.
  • Watermain has been placed along Cimarron between Goodwood and Tuscany.
    • The main has passed all testing and has been tied into the existing system.
    • Crews have continued stubbing water services out to the right of way line.
  • Watermain has been placed along Burger between Tuscany and Tanglewood including the bayou crossing.
    • The main has passed all testing and has been tied into the existing system.
  • Watermain has been placed along Burger between Tanglewood and the west end of the job limits (6950 Burger).
  • Contractor has begun the installation of the new storm sewer on Burger between Tanglewood and the bayou and between Tuscany and 6920 Burger.
  • Installation of the watermain on Tuscany has begun.

 

Work Upcoming

  • The contractor will continue stubbing water services on Cimarron.
  • The contractor will begin stubbing water services on Burger between Tuscany and Tanglewood
  • The Contractor anticipates that crews will complete storm sewer on Burger between Tanglewood and Goodwood.
  • Asphalt paving crews is scheduled to be on site by the end of the month to replace sections of road that were removed and begin replacement of drive approaches. This is dependent on weather condition suitable for paving.
  • Concrete driveway replacement will occur at a later date once an appropriate amount has been reached for the concrete crews to have a full day works
  • Contractor will also replace the guardrail that was removed by the Burger bayou in the coming weeks.
  • Watermain installation on Tuscany is also slated to continue.
  • Crews will continue restorative efforts in completed areas.

 

General Notes

  • The lane reduction/daytime closures on Burger between Tuscany and Tanglewood will remain in place until the storm sewer can be installed, the guardrail can be replaced, and the road reconstruction completed. It is anticipated that this will be completed by the end of the month.