Work Completed This Past Week:
- Crews removed concrete curb and gutter and driveway approaches.
- Water main pipe was installed from Sherman north towards Hume Street.
Work Anticipated Week of May 15, 2023
- Water main pipe installation up to Hume Street.
- Water main will be tested for leaks and disinfected to be tied into the existing water mains.
- Existing water main may be shut down for tie-ins. Affected customers will be notified ahead of time. Disruptions will last about 4-6 hours until the new water main is tied in safely.
Work Anticipated Week of May 22, 2023
- Water Service lines will begin to be replaced in the first block between Sherman and Hume.
- Water main pipe will continue to be placed up to Barney and in Hume between Baker and Leahy.