Work Completed This Past Week:

  • Crews removed concrete curb and gutter and driveway approaches.
  • Water main pipe was installed from Sherman north towards Hume Street.

 

Work Anticipated Week of May 15, 2023

  • Water main pipe installation up to Hume Street.
  • Water main will be tested for leaks and disinfected to be tied into the existing water mains.
  • Existing water main may be shut down for tie-ins. Affected customers will be notified ahead of time. Disruptions will last about 4-6 hours until the new water main is tied in safely.

 

Work Anticipated Week of May 22, 2023

  • Water Service lines will begin to be replaced in the first block between Sherman and Hume.
  • Water main pipe will continue to be placed up to Barney and in Hume between Baker and Leahy.