This Week:

  • Dean’s completed water service installation on Rogue Hollow Court.
  • Packer Woods Drive paving was completed.
  • Road patches were paved on Rogue Hollow Court and Rogue Hill Court.

 

Next Week:

  • Concrete driveways will be replaced on Packer Woods and Rogue Hill.
  • Dean’s will complete lawn restoration and final project clean up.

 

Please contact any project representative to the left if you have questions or concerns.