Work completed/in progress from this past week:

– 36″ transmission main construction progressed to approximately 700 west of 152nd.
– Drilling contractor continues to remove material for pipe installation beneath Pine Creek.
– Water service verification and replacement, as necessary.
– Waukazoo Elementary drives have all been returned to service. All traffic must enter from 160th to the west.
– Road building behind transmission main continues.

 

Anticipated activities for next week include:

– Lakewood will be closed from 144th to River. The hard road closure will be limited from 144th to Aniline. Thru traffic will be detoured to Douglas Ave.
– Continue transmission main construction.
– Drilling contractor will continue to remove material for pipe installation beneath Pine Creek.
– Continue road building behind transmission main construction.
– Water service verification and replacement.
– Dewatering setup.