Progress Update

Sanitary sewer installation along Francis Ave and Eastman Ave is mostly complete. The portion of the project has gone relatively smoothly, although slower than anticipated. Approximately 1,500 feet of sanitary sewer has been to installed to date which is about 20% of the total 6,750 feet involved on the project. The gravel roads, which include Francis (from Blaine to Eastman) and Eastman (from Francis to Norris), have also been restored.


Up Next

Sanitary sewer installation along Britain Ave is expected to begin during the coming week. Traffic will be detoured onto Empire Ave for several weeks or more while sewer construction on Britain is underway.