This Week
Elmer’s finished fine grading the aggregate base for the trail, and paved the first layer of asphalt on the trail section from The Cove area up past NMC to the end of the first phase. They also began prepping at Medalie park for the pathway improvements there, and the rest area/plaza going in at the park. They also prepped area for the concrete “node” rest areas along the path.
Next Week
We anticipate work will continue internally at Medalie Park on the rest area/plaza, as well as the trails. Also the old parking lot will soon be removed and repaved as well.