Work Completed This Week
- Connected 20 water services to the new water main
- Placed 2 storm catch basins and storm sewer leads
Anticipated Work Next Week
- Continue boring and connecting water services
- Continue placing storm sewer
- Perform two water main tie-ins on Tuesday, May 18 (expect temporary water disruption on Peck St. North of Strong Ave. and on Ionia St.)
- Begin rebuilding the roadway from the north end of project limits towards the south
- Begin removing the roadway for Phase 2 (between Southern and Laketon Avenues.) on Wednesday, May 19.