Progress Report

This week:

  • Schippers finished up water main construction along Bonneville Drive.
  • Schippers finished up water main construction along Rockhill Drive.
  • Schippers pressure tested the water main in Rockhill Drive and is pressure testing the water main in Bonneville Drive and Bonanza Drive today.
  • The pavement in Rockvalley Drive was removed in preparation for water main construction.

Next week:

  • Water service installation and final water main tie-in will be completed on Rockhill Drive Monday and Tuesday.
  • Schippers will disinfect the water main in Bonneville Drive and Bonanza Drive.
  • After the water main has been disinfected, the new water main will be tied into to the existing water main in 5 Mile Road, this is scheduled for Wednesday. After the water main tie-in is completed, Schippers will start to switch water services from the temporary water main to the new water main.
  • Schippers will be preparing the easement area for their tree clearing subcontractor, Integrity Tree Services, to remove the trees in the water main easement in preparation for water main installation later in the project.

Please contact a project representative if you have questions or concerns.

 

What to Expect

May

  • Water service installation on Rockhill Drive.
  • Water service installation on Bonneville Drive and Bonanza Drive between 5 Mile Road and Brisam Street.

Long Term

  • Schippers’ overall project schedule anticipates the total project, including road paving and lawn restoration, being complete in late summer. Schippers is currently on track to meet this schedule.

 

Mail & Trash

  • The contractor has set up a bank of temporary mailboxes on Brisam Street, west of Bonneville Drive. If you are within the construction area, your mail service has been temporarily relocated to here.
  • The contractor is also coordinating with the trash haulers in the area to ensure that the trash is picked up during construction. Please bring your cans to the end of your driveway as you typically would, and the contractor will move them as necessary for pickup and return them at the end of the day.

 

Projected Timeline

  • May – late-June
    • Water main and water service construction on Bonneville Dr. and Bonanaza Dr. between 5 Mile Rd. and Brisam St.
  • May
    • Water service construction along Plainfield Ave.
    • Water main and water service construction in Rockhill Dr.
    • Water main and water service construction in Rockvalley Dr.
  • late-June – late-September
    • Water main and water service construction on Bonneville Dr. and court streets north of Brisam St.