This week the focus was on water service installations, road rebuilding and water main connections. Road building started on Center Street with cutting for sand grade and placing aggregate. West Street focus was on water services and connecting the main to the system. Utility work is nearly complete!
Work Completed This Week on West
- All water main has now been tested and connected to the system. Connections were made at Oak Park on Friday.
- Water service installation continued north of Vine.
Work Completed This Week on Center
- Road rebuilding has begun grading for gravel placement. Gravel is being placed as the crews progress south.
Anticipated Work on Center
- Continuing on reconstruction of the roadway.
Anticipated Work on West
- Water service replacements will continue north of Vine and will start south of Vine.
- Water main connections are schedule for Monday on Vine.