Underground work has essentially wrapped up on the project! Road rebuilding will be the primary focus moving. Significant progress on the road reconstruction was also made with concrete curb and approaches being installed west of Gaylord.Work Completed This Week
- Utility work is now complete less a few minor finish items.
- Concrete curb and gutter was completed west of Gaylord.
- Concrete driveway approaches were completed west of Gaylord.
- Sidewalk ramps will be poured on Monday as well as remaining curb west of Gaylord.
- Final grading of the gravel west of Gaylord in preperation of paving.
- Grading for sand grade and spreading of gravel east of Gaylord will begin.
- Paving of the first layer of asphalt west of Gaylord is possibly by the end of the week but that schedule is not certain.