Progress Report: Completion is near for the final stages of the Jericho Trail. This week the crews graded and prepared the gravel grade for paving. The storm sewer construction is complete. Crews also completed the hydrant relocations since the last update.

Upcoming Work: The paving crew is planning to pave in the near future followed by topsoil and seeding along the remaining pathway. We anticipate that the trail will be fully open by the first week of June!