Progress Report:

This week CL Trucking and Excavating made a big push to get their restoration work completed ahead of the road repaving project. KCRC was also busy preparing for the upcoming road repaving project by replacing concrete curb and gutter and replacing manhole and catch basin covers as necessary.

Upcoming Work:

CL Trucking & Excavating will be back on site at some point in the future to complete some minor punch list items. They will coordinate this work with KCRC so that it does not interfere with the road repaving project.

KCRC’s contractor is scheduled to mill off the existing asphalt road surface next Wednesday (5/22). Soon after this is completed the base course of paving will be completed. KCRC intends to replace concrete driveways as needed before paving the final course of asphalt later in early June.