Progress Report:

This week, Dykema and the Township Water Department successfully disinfected the last section of water main and the connection to the existing transmission main was completed on Friday. See pictures below for some of this work in action. This marks the last portion of the water main work for the project and a significant milestone. The Township Water Department staff will be able to continue to supply clean reliable water to the NE portion of the Township for years to come.

Kuttshill Drive base course paving was completed on Wednesday and final paving is scheduled for tomorrow (Saturday). Michigan Paving and Materials will complete the top course paving on Kuttshill, pave the asphalt driveways along Northland Drive, and pave the patch in Brewer Avenue at M-44.

Upcoming Work:

Dykema will have crews on site next week to complete final lawn restoration and final project clean up.